Aviator Hotel Renovation

GENERAL INFORMATION

Location: Anchorage, Alaska
Type of Project: Abatement & Demolition
Project Duration: November 2022-July 2023
Contractor Type: Subcontractor

WORK DETAILS
Hazardous Materials Removed: Asbestos, Construction and Demolition Debris
Quantity Removed: 10,000 lbs
Scope of Work: This project consisted of the removal of asbestos containing fireproofing, existing mansard roof frames, cutting of roof joist tails and partial demolition of the structure.
Work Subcontracted: Air Monitoring
Overall Evaluation: Excellent

In August 2022 around 200 unsheltered people were staying at the Aviator Hotel. Photographed on Aug. 19, 2022. (Loren Holmes / ADN)